This collection includes most of the ASU Theses and Dissertations from 2011 to present. ASU Theses and Dissertations are available in downloadable PDF format; however, a small percentage of items are under embargo. Information about the dissertations/theses includes degree information, committee members, an abstract, supporting data or media.

In addition to the electronic theses found in the ASU Digital Repository, ASU Theses and Dissertations can be found in the ASU Library Catalog.

Dissertations and Theses granted by Arizona State University are archived and made available through a joint effort of the ASU Graduate College and the ASU Libraries. For more information or questions about this collection contact or visit the Digital Repository ETD Library Guide or contact the ASU Graduate College at gradformat@asu.edu.

Displaying 1 - 3 of 3
Filtering by

Clear all filters

152178-Thumbnail Image.png
Description
The construction industry in India suffers from major time and cost overruns. Data from government and industry reports suggest that projects suffer from 20 to 25 percent time and cost overruns. Waste of resources has been identified as a major source of inefficiency. Despite a substantial increase in the past

The construction industry in India suffers from major time and cost overruns. Data from government and industry reports suggest that projects suffer from 20 to 25 percent time and cost overruns. Waste of resources has been identified as a major source of inefficiency. Despite a substantial increase in the past few years, demand for professionals and contractors still exceeds supply by a large margin. The traditional methods adopted in the Indian construction industry may not suffice the needs of this dynamic environment, as they have produced large inefficiencies. Innovative ways of procurement and project management can satisfy the needs aspired to as well as bring added value. The problems faced by the Indian construction industry are very similar to those faced by other developing countries. The objective of this paper is to discuss and analyze the economic concerns, inefficiencies and investigate a model that both explains the Indian construction industry structure and provides a framework to improve efficiencies. The Best Value (BV) model is examined as an approach to be adopted in lieu of the traditional approach. This could result in efficient construction projects by minimizing cost overruns and delays, which until now have been a rarity.
ContributorsNihas, Syed (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Kashiwagi, Jacob (Committee member) / Arizona State University (Publisher)
Created2013
153835-Thumbnail Image.png
Description
Saudi Arabia has been having many issues with large construction projects such as delays, low performance and high cost. Some studies show that around 70% of the public projects in Saudi Arabia are delayed. These issues have resulted from many factors. One of the factors believed to be delaying projects

Saudi Arabia has been having many issues with large construction projects such as delays, low performance and high cost. Some studies show that around 70% of the public projects in Saudi Arabia are delayed. These issues have resulted from many factors. One of the factors believed to be delaying projects is the Saudi procurement system. The Saudi procurement system only selects contracts based on the lowest bid price offered. However, the Saudi procurement system has been found to not only produce delayed low quality projects, but also has resulted in higher costs.

This paper shows how to modify the Saudi procurement system by implementing a clarification phase, which is the most important phase in the Performance Information Procurement System (PIPS). The clarification phase requires the bid’s winning contractor to submit a project scope, a project schedule, to identify risks that not their responsibility, performance measurements and a milestone schedule. The PIPS system has been one of the most successful systems around the world and has shown a 98% success rate in six different countries with risks and cost reductions up to 30%.

This research conducted a survey of 157 engineers, 33 consultants, 9 owners, 5 vendors, 13 academics, and 28 architects to develop the public procurement system in Saudi Arabia. The participants work in government sectors with an interest in the Saudi Arabian procurement system. 80.61 % of participants believe that the traditional Saudi procurement system consistently selects poor performing contractors. Moreover, 95.97% of participants think that the selection of contractors based only on the lowest price criterion affects projects negatively. Also, 96.20% of participants in the survey feel that there needs to be a change in the traditional Saudi Arabian procurement system. 88.7% of participants agree to require the contractor to identify risks, and 96.03 % of participants agree that the contractors must have a plan. Moreover, 95.45% of participants agree to require a contractor review the scope of a project and verify that it is correct. Finally, 82.18% of participants agree to require a contractor to resolve all owner concerns before signing a contract to improve construction projects performance. The paper shows the need to change the Saudi procurement system and a solution to this growing problem.
ContributorsAlofi, Ahmed Abdulrahman (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Kashiwagi, Jacob (Committee member) / Arizona State University (Publisher)
Created2015
156379-Thumbnail Image.png
Description
Recent studies have identified that contractors in the Saudi construction industry are not the main party that cause risks as owners and other parties have the major share of causing risks. However, with the identification that risks out of contractors’ control are a leading cause of low performance, there is

Recent studies have identified that contractors in the Saudi construction industry are not the main party that cause risks as owners and other parties have the major share of causing risks. However, with the identification that risks out of contractors’ control are a leading cause of low performance, there is a lack of efficient risk mitigation practices in Saudi to manage these risks. The main aim of this dissertation is to assess the current practices applied by contractors to minimize risk out of their control and develop a risk mitigation model to manage these risks. The main objectives of the study are: investigating the risks that are out of contractors’ control, assessing the contractors’ current risk mitigation and performance measurement practices, and finally developing and validating a risk mitigation model to minimize risks out of contractors’ control and measure performance of involved project parties. To achieve the study aim, a mixed methodological approach was adopted. Theoretical approaches were utilized to review previous research and to develop a conceptual risk mitigation framework followed by a practical approach that is considered with collecting data from contractors. The quantitative method was mainly used to meet the study objectives through distributing a survey in the form of a questionnaire. As a consolidation of the study findings, the top ranked risks that are out of contractors’ control were identified. Furthermore, the results identified that the contractors’ current risk management and performance measurement practices are not effective in minimizing projects risks caused by other parties and ineffective in measuring performance of all parties. The developed model focuses on increasing accountability of project parties through mitigating project parties’ activities and risks with measuring the deviations and identifying sources of deviations. Transparency is utilized in the model through sharing weekly updates of the activities and risks combined with updated information of performance measurements of all project parties. The study results showed that project risks can be minimized and projects’ performance can be increased if contractors shift their focus using the developed model from only managing their own activities and risks to managing all project parties’ activities and risks.
ContributorsAlgahtany, Mohammed (Author) / Sullivan, Kenneth (Thesis advisor) / Kashiwagi, Dean (Committee member) / Badger, William (Committee member) / Arizona State University (Publisher)
Created2018