This collection includes most of the ASU Theses and Dissertations from 2011 to present. ASU Theses and Dissertations are available in downloadable PDF format; however, a small percentage of items are under embargo. Information about the dissertations/theses includes degree information, committee members, an abstract, supporting data or media.
In addition to the electronic theses found in the ASU Digital Repository, ASU Theses and Dissertations can be found in the ASU Library Catalog.
Dissertations and Theses granted by Arizona State University are archived and made available through a joint effort of the ASU Graduate College and the ASU Libraries. For more information or questions about this collection contact or visit the Digital Repository ETD Library Guide or contact the ASU Graduate College at gradformat@asu.edu.
Filtering by
- All Subjects: Civil Engineering
This paper shows how to modify the Saudi procurement system by implementing a clarification phase, which is the most important phase in the Performance Information Procurement System (PIPS). The clarification phase requires the bid’s winning contractor to submit a project scope, a project schedule, to identify risks that not their responsibility, performance measurements and a milestone schedule. The PIPS system has been one of the most successful systems around the world and has shown a 98% success rate in six different countries with risks and cost reductions up to 30%.
This research conducted a survey of 157 engineers, 33 consultants, 9 owners, 5 vendors, 13 academics, and 28 architects to develop the public procurement system in Saudi Arabia. The participants work in government sectors with an interest in the Saudi Arabian procurement system. 80.61 % of participants believe that the traditional Saudi procurement system consistently selects poor performing contractors. Moreover, 95.97% of participants think that the selection of contractors based only on the lowest price criterion affects projects negatively. Also, 96.20% of participants in the survey feel that there needs to be a change in the traditional Saudi Arabian procurement system. 88.7% of participants agree to require the contractor to identify risks, and 96.03 % of participants agree that the contractors must have a plan. Moreover, 95.45% of participants agree to require a contractor review the scope of a project and verify that it is correct. Finally, 82.18% of participants agree to require a contractor to resolve all owner concerns before signing a contract to improve construction projects performance. The paper shows the need to change the Saudi procurement system and a solution to this growing problem.
The objective of this dissertation is to identify a recommended balance between
leadership and management activities of a project manager who aims to rehabilitate a distressed construction project.
The data for this research was collected from 338 construction project professionals belonging to fifteen large construction companies who participated in leadership seminars originated by professors from Arizona State University. The seminars contained various leadership games and exercises that were designed specifically to collect data about leadership and management actions taken by the project managers.
The data from one of the games, called “Project from Hell” (PFH), was used in this research. The PFH game presents the participants with a set of fifty-two actions cards written on a deck of game cards and asks them to select the ten action cards they perceive as being most effective for turning a troubled construction project around. Each suit of the deck represents a different category of actions, focusing on either Traditional Leadership (Hearts), Best Value Leadership (Diamonds), Traditional Management (Spades), or Micro- Management (Clubs).
Statistical analysis of the results revealed that only sixteen of the fifty-two actions cards were selected with statistically significant consistency. Of these sixteen actions, six actions were form Traditional Management actions, five were Traditional Leadership actions, and five were Best Value Leadership actions. This rendered a recommended balance of 62% leadership activities vs. 38% management activities for project managers to rehabilitate distressed construction projects. It was also found that the same balance is recommended for the normal condition construction projects. The calculated weighted
i
scores for ranking the sixteen effective leadership and management actions revealed that the five Traditional Management actions are the top-most effective actions. This demonstrates the importance of stand still management actions in rehabilitating in trouble construction projects
The findings were converted into easy to implement guidelines about how project managers can change habits to increase their effectiveness by focusing on the right type of actions.
A generalization of the methodology for interpreting the results of any study based on selection of activities, was also developed.
The current Saudi Arabian (SA) procurement system leads to many losses in money and benefits in projects. Also, the use of the traditional procurement system in SA has been identified as one of the causes for poor performance in the delivery of construction and the major risk to the SA government. A questionnaire has been developed and carefully designed based on literature review. The purpose of the survey was to identify the validity of the recent claims that the procurement system in SA is broken and to improve the current SA procurement system. The questionnaire was sent out to 1,396 participants including included 867 engineers, 256 consultants, 93 contractors, 35 owners and 132 architects and 13 academics.
All participants have been registered and licensed professionals at the SA Council for professional engineers, who work in both private and public sectors. The participants are interested in the SA procurement and contracts system with experience ranging from one to more than twenty-five years with the majority of twenty-five years of experience in common construction sectors such as; residential and commercial buildings, healthcare buildings, industrial building and heavy civil construction.
Most of the participants from both private and public sectors agreed with the survey questions subject matter regarding: zone price proposals, contractors' evaluation, risks, planning, projects' scope, owners concern and weekly risks reports (WRR). The survey results showed that the procurement system is the major risk to projects, affects construction projects negatively and is in need of improvement.
Based on the survey and literature review, a model, called Saudi government performance procurement model (SGPPM), has been developed in which the most expert contractor is chosen through four phases: submittals& education, vendors selection, illustration and execution. The resulting model is easy to implement by SA government and does not require special skills or backgrounds.