This dissertation fills the crucial knowledge gap in contract administration functions and tools for DB and CM/GC highway project delivery. First, this research identifies and models contract administration functions in DBB, CM/GC, and DB using integrated definition modeling (IDEF0). Second, this research identifies and analyzes DB and CM/GC tools for contract administration by conducting 30 ACM project case studies involving over 90 ACM practitioners. Recommendations on appropriate use regarding project phase, complexity, and size were gathered from 16 ACM practitioners. Third, the alternative technical concepts tool was studied. Data from 30 DB projects was analyzed to explore the timing of DB procurement and DB initial award performance in relation to the project influence curve. Types of innovations derived from ATCs are discussed. Considerable industry input at multiple stages grounds this research in professional practice.
Results indicate that the involvement of the contractor during the design phase for both DB and CM/GC delivery creates unique contract administration functions that need unique tools. Thirty-six DB and CM/GC tools for contract administration are identified with recommendations for effective implementation. While strong initial award performance is achievable in DB projects, initial award performance in this sample of projects is only loosely tied to the level of percent base design at procurement. Cost savings typically come from multiple ATCs, and innovations tend to be incremental rather than systemic, disruptive, or radical. Opportunity for innovation on DB highway projects is influenced by project characteristics and engaging the DB entity after pre-project planning.
The built environment is responsible for a significant portion of global waste generation.
Construction and demolition (C&D) waste requires significant landfill areas and costs
billions of dollars. New business models that reduce this waste may prove to be financially
beneficial and generally more sustainable. One such model is referred to as the “Circular
Economy” (CE), which promotes the efficient use of materials to minimize waste
generation and raw material consumption. CE is achieved by maximizing the life of
materials and components and by reclaiming the typically wasted value at the end of their
life. This thesis identifies the potential opportunities for using CE in the built environment.
It first calculates the magnitude of C&D waste and its main streams, highlights the top
C&D materials based on weight and value using data from various regions, identifies the
top C&D materials’ current recycling and reuse rates, and finally estimates a potential
financial benefit of $3.7 billion from redirecting C&D waste using the CE concept in the
United States.
as front end planning (FEP), have a large impact on project success and significant
influence on the configuration of the final project. As a key component of FEP, front end
engineering design (FEED) plays an essential role in the overall success of large industrial
projects. The primary objective of this dissertation focuses on FEED maturity and accuracy
and its impact on project performance. The author was a member of the Construction
Industry Institute (CII) Research Team (RT) 331, which was tasked to develop the FEED
Maturity and Accuracy Total Rating System (FEED MATRS), pronounced “feed matters.”
This dissertation provides the motivation, methodology, data analysis, research findings
(which include significant correlations between the maturity and accuracy of FEED and
project performance), applicability and contributions to academia and industry. A scientific
research methodology was employed in this dissertation that included a literature review,
focus groups, an industry survey, data collection workshops, in-progress projects testing,
and statistical analysis of project performance. The results presented in this dissertation are
based on input from 128 experts in 57 organizations and a data sample of 33 completed
and 11 on-going large industrial projects representing over $13.9 billion of total installed
cost. The contributions of this work include: (1) developing a tested FEED definition for
the large industrial projects sector, (2) determining the industry’s state of practice for
measuring FEED deliverables, (3) developing an objective and scalable two-dimensional
method to measure FEED maturity and accuracy, and (4) quantifying that projects with
high FEED maturity and accuracy outperformed projects with low FEED maturity and
accuracy by 24 percent in terms of cost growth, in relation to the approved budget.