Trenchless technologies have emerged as a viable alternative to traditional open trench methods for installing underground pipelines and conduits. Pilot Tube Microtunneling, also referred to as the pilot tube system of microtunneling, guided auger boring, or guided boring method, is a recent addition to the family of trenchless installation methods.

Trenchless technologies have emerged as a viable alternative to traditional open trench methods for installing underground pipelines and conduits. Pilot Tube Microtunneling, also referred to as the pilot tube system of microtunneling, guided auger boring, or guided boring method, is a recent addition to the family of trenchless installation methods. Pilot tube microtunneling originated in Japan and Europe, and was introduced to the United States in the year 1995 (Boschert 2007). Since then this methodology has seen increased utilization across North America particularity in municipal markets for the installation of gravity sewers. The primary reason contributing to the growth of pilot tube microtunneling is the technology's capability of installing pipes at high precision in terms of line and grade, in a wide range of ground conditions using relatively inexpensive equipment. The means and methods, applicability, capabilities and limitations of pilot tube microtunneling are well documented in published literature through many project specific case studies. However, there is little information on the macroscopic level regarding the technology and industry as a whole. With the increasing popularity of pilot tube microtunneling, there is an emerging need to address the above issues. This research effort surveyed 22 pilot tube microtunneling contractors across North America to determine the current industry state of practice with the technology. The survey examined various topics including contractor profile and experience; equipment, methods, and pipe materials utilized; and issues pertaining to project planning and construction risks associated with the pilot tube method. The findings of this research are based on a total of 450 projects completed with pilot tube microtunneling between 2006 and 2010. The respondents were diverse in terms of their experience with PTMT, ranging from two to 11 years. A majority of the respondents have traditionally provided services with other trenchless technologies. As revealed by the survey responses, PTMT projects grew by 110% between the years 2006 and 2010. It was found that almost 72% of the 450 PTMT projects completed between 2006 and 2010 by the respondents were for sanitary sewers. Installation in cobbles and boulders was rated as the highest risk by the contractors.
ContributorsGottipati, Vamseedhar (Author) / Lueke, Jason S (Thesis advisor) / Ariaratnam, Samuel T (Committee member) / Chasey, Allan (Committee member) / Arizona State University (Publisher)
Created2011
151597-Thumbnail Image.png
Description
Trenchless technology is a group of techniques whose utilization allows for the installation, rehabilitation, and repair of underground infrastructure with minimal excavation from the ground surface. As the built environment becomes more congested, projects are trending towards using trenchless technologies for their ability to quickly produce a quality product with

Trenchless technology is a group of techniques whose utilization allows for the installation, rehabilitation, and repair of underground infrastructure with minimal excavation from the ground surface. As the built environment becomes more congested, projects are trending towards using trenchless technologies for their ability to quickly produce a quality product with minimal environmental and social costs. Pilot tube microtunneling (PTMT) is a trenchless technology where new pipelines may be installed at accurate and precise line and grade over manhole to manhole distances. The PTMT process can vary to a certain degree, but typically involves the following three phases: jacking of the pilot tube string to achieve line and grade, jacking of casing along the pilot bore and rotation of augers to excavate the borehole to a diameter slightly larger than the product pipe, and jacking of product pipe directly behind the last casing. Knowledge of the expected productivity rates and jacking forces during a PTMT installation are valuable tools that can be used for properly weighing its usefulness versus competing technologies and minimizing risks associated with PTMT. This thesis outlines the instrumentation and monitoring process used to record jacking frame hydraulic pressures from seven PTMT installations. Cyclic patterns in the data can be detected, indicating the installation of a single pipe segment, and enabling productivity rates for each PTMT phase to be determined. Furthermore, specific operations within a cycle, such as pushing a pipe or retracting the machine, can be observed, allowing for identification of the critical tasks associated with each phase. By identifying the critical tasks and developing more efficient means for their completion, PTMT productivity can be increased and costs can be reduced. Additionally, variations in depth of cover, drive length, pipe diameter, and localized ground conditions allowed for trends in jacking forces to be identified. To date, jacking force predictive models for PTMT are non-existent. Thus, jacking force data was compared to existing predictive models developed for the closely related pipe jacking and microtunneling methodologies, and the applicability of their adoption for PTMT jacking force prediction was explored.
ContributorsOlson, Matthew P (Author) / Ariaratnam, Samuel T (Thesis advisor) / Lueke, Jason S (Committee member) / Zapata, Claudia E (Committee member) / Tang, Pingbo (Committee member) / Arizona State University (Publisher)
Created2013
150567-Thumbnail Image.png
Description
Nowadays there is a pronounced interest in the need for sustainable and reliable infrastructure systems to address the challenges of the future infrastructure development. This dissertation presents the research associated with understanding various sustainable and reliable design alternatives for water distribution systems. Although design of water distribution networks (WDN) is

Nowadays there is a pronounced interest in the need for sustainable and reliable infrastructure systems to address the challenges of the future infrastructure development. This dissertation presents the research associated with understanding various sustainable and reliable design alternatives for water distribution systems. Although design of water distribution networks (WDN) is a thoroughly studied area, most researchers seem to focus on developing algorithms to solve the non-linear hard kind of optimization problems associated with WDN design. Cost has been the objective in most of the previous studies with few models considering reliability as a constraint, and even fewer models accounting for the environmental impact of WDN. The research presented in this dissertation combines all these important objectives into a multi-objective optimization framework. The model used in this research is an integration of a genetic algorithm optimization tool with a water network solver, EPANET. The objectives considered for the optimization are Life Cycle Costs (LCC) and Life Cycle Carbon Dioxide (CO2) Emissions (LCE) whereby the system reliability is made a constraint. Three popularly used resilience metrics were investigated in this research for their efficiency in aiding the design of WDNs that are able to handle external natural and man-made shocks. The best performing resilience metric is incorporated into the optimization model as an additional objective. Various scenarios were developed for the design analysis in order to understand the trade-offs between different critical parameters considered in this research. An approach is proposed and illustrated to identify the most sustainable and resilient design alternatives from the solution set obtained by the model employed in this research. The model is demonstrated by using various benchmark networks that were studied previously. The size of the networks ranges from a simple 8-pipe system to a relatively large 2467-pipe one. The results from this research indicate that LCE can be reduced at a reasonable cost when a better design is chosen. Similarly, resilience could also be improved at an additional cost. The model used in this research is more suitable for water distribution networks. However, the methodology could be adapted to other infrastructure systems as well.
ContributorsPiratla, Kalyan Ram (Author) / Ariaratnam, Samuel T (Thesis advisor) / Chasey, Allan (Committee member) / Lueke, Jason (Committee member) / Arizona State University (Publisher)
Created2012
Description
Horizontal Directional Drilling (HDD) is a growing and expanding trenchless method utilized to install pipelines from 2 to 60 inch diameters for lengths over 10,000 foot. To date, there are not many public documents where direct costs and bid prices incurred by HDD installations are available and analyzed. The objective

Horizontal Directional Drilling (HDD) is a growing and expanding trenchless method utilized to install pipelines from 2 to 60 inch diameters for lengths over 10,000 foot. To date, there are not many public documents where direct costs and bid prices incurred by HDD installations are available and analyzed. The objective is to provide a better understanding of the factors affecting the bid prices of these projects. The first section of the thesis analyzes how project parameters such as product diameter, bore length and soil conditions affect the bid price of water and wastewater pipeline installations using HDD. Through multiple linear regressions, the effect of project parameters on bid prices of small, medium and large rigs projects is extracted. The results were further investigated to gain a better understanding of bid factors that influence the relationship between total cost and the project parameters. The second section uses unit cost, based on bid prices, to compare the costs incurred by defined categories. Parameters such as community type, product type, soil conditions, and geographical region were used in the analysis. Furthermore, using average unit cost from 2001 to 2009, HDD project cost trends are briefly analyzed against the main variations of the US economy from the same time horizon by using economic indicators. It was determined that project geometric factors influence more the bid price of small rig projects than large rig projects because external factors including market rates and economic situation have an increasing impact on bid prices when rig size increases. It was observed that bid price variation of HDD projects over years followed the same trend as the US economic variation described by economic indicators.
ContributorsVilfrant, Emmania Claudyne (Author) / Ariaratnam, Samuel T (Thesis advisor) / Lueke, Jason S (Committee member) / Chasey, Allan D (Committee member) / Arizona State University (Publisher)
Created2010
134875-Thumbnail Image.png
Description
Productivity in the construction industry is an essential measure of production efficiency and economic progress, quantified by craft laborers' time spent directly adding value to a project. In order to better understand craft labor productivity as an aspect of lean construction, an activity analysis was conducted at the Arizona State

Productivity in the construction industry is an essential measure of production efficiency and economic progress, quantified by craft laborers' time spent directly adding value to a project. In order to better understand craft labor productivity as an aspect of lean construction, an activity analysis was conducted at the Arizona State University Palo Verde Main engineering dormitory construction site in December of 2016. The objective of this analysis on craft labor productivity in construction projects was to gather data regarding the efficiency of craft labor workers, make conclusions about the effects of time of day and other site-specific factors on labor productivity, as well as suggest improvements to implement in the construction process. Analysis suggests that supporting tasks, such as traveling or materials handling, constitute the majority of craft labors' efforts on the job site with the highest percentages occurring at the beginning and end of the work day. Direct work and delays were approximately equal at about 20% each hour with the highest peak occurring at lunchtime between 10:00 am and 11:00 am. The top suggestion to improve construction productivity would be to perform an extensive site utilization analysis due to the confined nature of this job site. Despite the limitations of an activity analysis to provide a complete prospective of all the factors that can affect craft labor productivity as well as the small number of days of data acquisition, this analysis provides a basic overview of the productivity at the Palo Verde Main construction site. Through this research, construction managers can more effectively generate site plans and schedules to increase labor productivity.
ContributorsFord, Emily Lucile (Author) / Grau, David (Thesis director) / Chong, Oswald (Committee member) / Civil, Environmental and Sustainable Engineering Programs (Contributor) / School of International Letters and Cultures (Contributor) / Barrett, The Honors College (Contributor)
Created2016-12
134662-Thumbnail Image.png
Description
The overall energy consumption around the United States has not been reduced even with the advancement of technology over the past decades. Deficiencies exist between design and actual energy performances. Energy Infrastructure Systems (EIS) are impacted when the amount of energy production cannot be accurately and efficiently forecasted. Inaccurate engineering

The overall energy consumption around the United States has not been reduced even with the advancement of technology over the past decades. Deficiencies exist between design and actual energy performances. Energy Infrastructure Systems (EIS) are impacted when the amount of energy production cannot be accurately and efficiently forecasted. Inaccurate engineering assumptions can result when there is a lack of understanding on how energy systems can operate in real-world applications. Energy systems are complex, which results in unknown system behaviors, due to an unknown structural system model. Currently, there exists a lack of data mining techniques in reverse engineering, which are needed to develop efficient structural system models. In this project, a new type of reverse engineering algorithm has been applied to a year's worth of energy data collected from an ASU research building called MacroTechnology Works, to identify the structural system model. Developing and understanding structural system models is the first step in creating accurate predictive analytics for energy production. The associative network of the building's data will be highlighted to accurately depict the structural model. This structural model will enhance energy infrastructure systems' energy efficiency, reduce energy waste, and narrow the gaps between energy infrastructure design, planning, operation and management (DPOM).
ContributorsCamarena, Raquel Jimenez (Author) / Chong, Oswald (Thesis director) / Ye, Nong (Committee member) / Industrial, Systems (Contributor) / Barrett, The Honors College (Contributor)
Created2016-12
135209-Thumbnail Image.png
Description
Building construction, design and maintenance is a sector of engineering where improved efficiency will have immense impacts on resource consumption and environmental health. This research closely examines the Leadership in Environment and Energy Design (LEED) rating system and the International Green Construction Code (IgCC). The IgCC is a model code,

Building construction, design and maintenance is a sector of engineering where improved efficiency will have immense impacts on resource consumption and environmental health. This research closely examines the Leadership in Environment and Energy Design (LEED) rating system and the International Green Construction Code (IgCC). The IgCC is a model code, written with the same structure as many building codes. It is a standard that can be enforced if a city's government decides to adopt it. When IgCC is enforced, the buildings either meet all of the requirements set forth in the document or it fails to meet the code standards. The LEED Rating System, on the other hand, is not a building code. LEED certified buildings are built according to the standards of their local jurisdiction and in addition to that, building owners can chose to pursue a LEED certification. This is a rating system that awards points based on the sustainable measures achieved by a building. A comparison of these green building systems highlights their accomplishments in terms of reduced electricity usage, usage of low-impact materials, indoor environmental quality and other innovative features. It was determined that in general IgCC is more holistic, stringent approach to green building. At the same time the LEED rating system a wider variety of green building options. In addition, building data from LEED certified buildings was complied and analyzed to understand important trends. Both of these methods are progressing towards low-impact, efficient infrastructure and a side-by-side comparison, as done in this research, shed light on the strengths and weaknesses of each method, allowing for future improvements.
ContributorsCampbell, Kaleigh Ruth (Author) / Chong, Oswald (Thesis director) / Parrish, Kristen (Committee member) / Civil, Environmental and Sustainable Engineering Programs (Contributor) / Barrett, The Honors College (Contributor)
Created2016-05
133914-Thumbnail Image.png
Description
This paper describes the research done to quantify the relationship between external air temperature and energy consumption and internal air temperature and energy consumption. The study was conducted on a LEED Gold certified building, College Avenue Commons, located on Arizona State University's Tempe campus. It includes information on the background

This paper describes the research done to quantify the relationship between external air temperature and energy consumption and internal air temperature and energy consumption. The study was conducted on a LEED Gold certified building, College Avenue Commons, located on Arizona State University's Tempe campus. It includes information on the background of previous studies in the area, some that agree with the research hypotheses and some that take a different path. Real-time data was collected hourly for energy consumption and external air temperature. Intermittent internal air temperature was collected by undergraduate researcher, Charles Banke. Regression analysis was used to prove two research hypotheses. The authors found no correlation between external air temperature and energy consumption, nor did they find a relationship between internal air temperature and energy consumption. This paper also includes recommendations for future work to improve the study.
ContributorsBanke, Charles Michael (Author) / Chong, Oswald (Thesis director) / Parrish, Kristen (Committee member) / Mechanical and Aerospace Engineering Program (Contributor) / Barrett, The Honors College (Contributor)
Created2018-05
158113-Thumbnail Image.png
Description
The Chinese Construction Industry has grown to be one of the largest construction markets in the world within the last 10 years. The size of the Chinese Construction Industry is on par with many developed nations, despite it being a developing country. Despite its rapid growth, the productivity and profitability

The Chinese Construction Industry has grown to be one of the largest construction markets in the world within the last 10 years. The size of the Chinese Construction Industry is on par with many developed nations, despite it being a developing country. Despite its rapid growth, the productivity and profitability of the Chinese Construction Industry is low compared to similar sized construction industries (United States, United Kingdom, etc.). In addition to the low efficiency of the Chinese Construction Industry, there is minimal documentation available showing the performance of the Chinese Construction Industry (projects completed on time, on budget, and customer satisfaction ratings).

The purpose of this research is to investigate potential solutions that could address the poor efficiency and performance of the Chinese Construction Industry. This research is divided into three phases; first, a literature review to identify countries that have similar construction industries to the Chinese Construction Industry. The second phase is to compare the risks and identify solutions that are proposed to increase the performance of similar construction industries and the Chinese Construction Industry. The third phase is to create a survey from the literature-based information to validate the concepts with the Chinese Construction Industry professionals and stakeholders.
ContributorsChen, Yutian (Author) / Chong, Oswald (Thesis advisor) / Kashiwagi, Dean T. (Committee member) / Badger, Willliam (Committee member) / Arizona State University (Publisher)
Created2020
190881-Thumbnail Image.png
Description
The management of underground utilities is a complex and challenging task due to the uncertainty regarding the location of existing infrastructure. The lack of accurate information often leads to excavation-related damages, which pose a threat to public safety. In recent years, advanced underground utilities management systems have been developed to

The management of underground utilities is a complex and challenging task due to the uncertainty regarding the location of existing infrastructure. The lack of accurate information often leads to excavation-related damages, which pose a threat to public safety. In recent years, advanced underground utilities management systems have been developed to improve the safety and efficiency of excavation work. This dissertation aims to explore the potential applications of blockchain technology in the management of underground utilities and reduction of excavation-related damage. The literature review provides an overview of the current systems for managing underground infrastructure, including Underground Infrastructure Management (UIM) and 811, and highlights the benefits of advanced underground utilities management systems in enhancing safety and efficiency on construction sites. The review also examines the limitations and challenges of the existing systems and identifies the opportunities for integrating blockchain technology to improve their performance. The proposed application involves the creation of a shared database of information about the location and condition of pipes, cables, and other underground infrastructure, which can be updated in real time by authorized users such as utility companies and government agencies. The use of blockchain technology can provide an additional layer of security and transparency to the system, ensuring the reliability and accuracy of the information. Contractors and excavation companies can access this information before commencing work, reducing the risk of accidental damage to underground utilities.
ContributorsAlnahari, Mohammed S (Author) / Ariaratnam, Samuel T (Thesis advisor) / El Asmar, Mounir (Committee member) / Czerniawski, Thomas (Committee member) / Arizona State University (Publisher)
Created2023