Delays are a major cause for concern in the construction industry both globally and locally in Saudi Arabia. This paper identifies the main causes of delay in infrastructure projects in the holy city of Makkah (Saudi Arabia) and compares these with projects around the rest of the country and other

Delays are a major cause for concern in the construction industry both globally and locally in Saudi Arabia. This paper identifies the main causes of delay in infrastructure projects in the holy city of Makkah (Saudi Arabia) and compares these with projects around the rest of the country and other Gulf countries as well. Data were obtained from 49 infrastructure projects that were undertaken by the owner and were analyzed quantitatively to understand the severity and causes of delay. 10 risk factors were identified in this study and these factors were grouped into four categories. The average delay in infrastructure projects in the city of Makkah was found to be 39%. The most severe cause of delay was found to be the land acquisition factor. This highlights the critical land ownership and acquisition issues that is prevailing in Makkah. In addition to this, other factors include contractors’ lack of expertise, haphazard underground utilities (line services), and re-designing. It is concluded that majority of delays were caused from the owner’s side as compared to contractors, consultants, and other project’s stakeholders. This finding was in line with the research findings of the Gulf Countries Construction (GCC) Industry’s literature as well. This study will fill an important practice and research gap for improving the efficiency in project delivery for infrastructure projects in the holy city of Makkah and the Gulf countries at large.
ContributorsElawi, Ghazi Saad A (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Kashiwagi, Jacob (Committee member) / Arizona State University (Publisher)
Created2015
153835-Thumbnail Image.png
Description
Saudi Arabia has been having many issues with large construction projects such as delays, low performance and high cost. Some studies show that around 70% of the public projects in Saudi Arabia are delayed. These issues have resulted from many factors. One of the factors believed to be delaying projects

Saudi Arabia has been having many issues with large construction projects such as delays, low performance and high cost. Some studies show that around 70% of the public projects in Saudi Arabia are delayed. These issues have resulted from many factors. One of the factors believed to be delaying projects is the Saudi procurement system. The Saudi procurement system only selects contracts based on the lowest bid price offered. However, the Saudi procurement system has been found to not only produce delayed low quality projects, but also has resulted in higher costs.

This paper shows how to modify the Saudi procurement system by implementing a clarification phase, which is the most important phase in the Performance Information Procurement System (PIPS). The clarification phase requires the bid’s winning contractor to submit a project scope, a project schedule, to identify risks that not their responsibility, performance measurements and a milestone schedule. The PIPS system has been one of the most successful systems around the world and has shown a 98% success rate in six different countries with risks and cost reductions up to 30%.

This research conducted a survey of 157 engineers, 33 consultants, 9 owners, 5 vendors, 13 academics, and 28 architects to develop the public procurement system in Saudi Arabia. The participants work in government sectors with an interest in the Saudi Arabian procurement system. 80.61 % of participants believe that the traditional Saudi procurement system consistently selects poor performing contractors. Moreover, 95.97% of participants think that the selection of contractors based only on the lowest price criterion affects projects negatively. Also, 96.20% of participants in the survey feel that there needs to be a change in the traditional Saudi Arabian procurement system. 88.7% of participants agree to require the contractor to identify risks, and 96.03 % of participants agree that the contractors must have a plan. Moreover, 95.45% of participants agree to require a contractor review the scope of a project and verify that it is correct. Finally, 82.18% of participants agree to require a contractor to resolve all owner concerns before signing a contract to improve construction projects performance. The paper shows the need to change the Saudi procurement system and a solution to this growing problem.
ContributorsAlofi, Ahmed Abdulrahman (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Kashiwagi, Jacob (Committee member) / Arizona State University (Publisher)
Created2015
155168-Thumbnail Image.png
Description
Saudi Arabia has been facing issues with completing construction projects on time and on budget. It has been documented that 70% of public construction projects are delayed. Studies have identified the low-bid delivery method as an important factor in causing such delays. The procurement system (low-bid) ignores contractors’ performance, and

Saudi Arabia has been facing issues with completing construction projects on time and on budget. It has been documented that 70% of public construction projects are delayed. Studies have identified the low-bid delivery method as an important factor in causing such delays. The procurement system (low-bid) ignores contractors’ performance, and that is reflected in projects’ performance. A case study was performed, at a University campus in northern Saudi Arabia, identifying the major causes of project delays and cost overruns. The University was experiencing delays from 50% to 150%. Also, the actual project costs for four projects were examined and found that all four projects’ costs were higher than the original bid. The delay and cost overruns factors were gathered from the University engineers. A literature research identified one construction management method, best value performance information procurement system (BV PIPS), has documented multiple times its ability to improve project performance. In a comparison using the result of a case study and the results of (BV PIPS), Saudi Arabia’s delivery system was identified as a potential cause of project performance issues. The current procurement system was analyzed and modified to adapt with the (BV PIPS). The proposed procurement system using BV PIPS, which can be implemented in Saudi Arabia, was created with owner side. A large survey was conducted of 761 classified contractors and 43 universities’ representatives who rated causes of delay factors and cost overruns. The delay factors were then compared to delay factors experienced on Saudi construction projects, identified by performing a literature research. The comparison identified 14 important causes of delays. Moreover, the survey showed that classified contractors and universities’ representatives unsatisfied with low-bid, and they agreed with BV PIPS which selecting vendors based on performance with price. The proposed model required a submitted level of experience (LE), risk assessment (RA), and value added (VA). Besides, project managers of vendors should be interviewed during the clarification phase. In addition, venders should submit the project’s scope, technical schedule, milestone schedule, and risk management plan. In the execution phase, vendors should submit a weekly risk report (WRR) and director’s report (DR).
ContributorsAlzara, Majed (Author) / Kashiwagi, Dean (Thesis advisor) / Kashiwagi, Jacob (Committee member) / Al-Tassan, Abdulrahman (Committee member) / Arizona State University (Publisher)
Created2016
135520-Thumbnail Image.png
Description
With the help of some Information Measurement Theory (IMT), Kashiwagi Solutions Model (KSM), and deductive logic background, supply chain managers can start utilizing a new way to effectively and efficiently negotiate contracts. Developed by Dr. Dean Kashiwagi, the Best Value Approach has been 98% successful with over 1,800 projects for

With the help of some Information Measurement Theory (IMT), Kashiwagi Solutions Model (KSM), and deductive logic background, supply chain managers can start utilizing a new way to effectively and efficiently negotiate contracts. Developed by Dr. Dean Kashiwagi, the Best Value Approach has been 98% successful with over 1,800 projects for the past 20 years. The process gives vendors/suppliers the power to use their expertise. In return for not having to follow the rules set by the client/buyer, the vendor must show documentation and plans of risk management, value added processes, and metrics.
ContributorsPhan, Alice (Co-author) / Holtzman, Krista (Co-author) / Kashiwagi, Dean (Thesis director) / Kashiwagi, Jacob (Committee member) / School of International Letters and Cultures (Contributor) / Department of Supply Chain Management (Contributor) / Barrett, The Honors College (Contributor)
Created2016-05