Matching Items (4)
Filtering by

Clear all filters

153400-Thumbnail Image.png
Description
Economic and environmental concerns necessitate the preference for retrofits over new construction in manufacturing facilities for incorporating modern technology, expanding production, becoming more energy-efficient and improving operational efficiency. Despite the technical and functional challenges in retrofits, the expectation from the project team is to; reduce costs, ensure the time to

Economic and environmental concerns necessitate the preference for retrofits over new construction in manufacturing facilities for incorporating modern technology, expanding production, becoming more energy-efficient and improving operational efficiency. Despite the technical and functional challenges in retrofits, the expectation from the project team is to; reduce costs, ensure the time to market and maintain a high standard for quality and safety. Thus, the construction supply chain faces increasing pressure to improve performance by ensuring better labor productivity, among other factors, for efficiency gain. Building Information Modeling (BIM) & off-site prefabrication are determined as effective management & production methods to meet these goals. However, there are limited studies assessing their impact on labor productivity within the constraints of a retrofit environment. This study fills the gap by exploring the impact of BIM on labor productivity (metric) in retrofits (context).

BIM use for process tool installation at a semiconductor manufacturing facility serves as an ideal environment for practical observations. Direct site observations indicate a positive correlation between disruptions in the workflow attributed to an immature use of BIM, waste due to rework and high non-value added time at the labor work face. Root-cause analysis traces the origins of the said disruptions to decision-factors that are critical for the planning, management and implementation of BIM. Analysis shows that stakeholders involved in decision-making during BIM planning, management and implementation identify BIM-value based on their immediate utility for BIM-use instead of the utility for the customers of the process. This differing value-system manifests in the form of unreliable and inaccurate information at the labor work face.

Grounding the analysis in theory and observations, the author hypothesizes that stakeholders of a construction project value BIM and BIM-aspects (i.e. geometrical information, descriptive information and workflows) differently and the accuracy of geometrical information is critical for improving labor productivity when using prefabrication in retrofit construction. In conclusion, this research presents a BIM-value framework, associating stakeholders with their relative value for BIM, the decision-factors for the planning, management and implementation of BIM and the potential impact of those decisions on labor productivity.
ContributorsGhosh, Arundhati (Author) / Chasey, Allan D (Thesis advisor) / Laroche, Dominique-Claude (Committee member) / Fowler, John (Committee member) / Arizona State University (Publisher)
Created2015
150981-Thumbnail Image.png
Description
For more than twenty years, clinical researchers have been publishing data regarding incidence and risk of adverse events (AEs) incurred during hospitalizations. Hospitals have standard operating policies and procedures (SOPP) to protect patients from AE. The AE specifics (rates, SOPP failures, timing and risk factors) during heart failure (HF) hospitalizations

For more than twenty years, clinical researchers have been publishing data regarding incidence and risk of adverse events (AEs) incurred during hospitalizations. Hospitals have standard operating policies and procedures (SOPP) to protect patients from AE. The AE specifics (rates, SOPP failures, timing and risk factors) during heart failure (HF) hospitalizations are unknown. There were 1,722 patients discharged with a primary diagnosis of HF from an academic hospital between January 2005 and December 2007. Three hundred eighty-one patients experienced 566 AEs, classified into four categories: medication (43.9%), infection (18.9%), patient care (26.3%), or procedural (10.9%). Three distinct analyses were performed: 1) patient's perspective of SOPP reliability including cumulative distribution and hazard functions of time to AEs; 2) Cox proportional hazards model to determine independent patient-specific risk factors for AEs; and 3) hospital administration's perspective of SOPP reliability through three years of the study including cumulative distribution and hazard functions of time between AEs and moving range statistical process control (SPC) charts for days between failures of each type. This is the first study, to our knowledge, to consider reliability of SOPP from both the patient's and hospital administration's perspective. AE rates in hospitalized patients are similar to other recently published reports and did not improve during the study period. Operations research methodologies will be necessary to improve reliability of care delivered to hospitalized patients.
ContributorsHuddleston, Jeanne (Author) / Fowler, John (Thesis advisor) / Montgomery, Douglas C. (Thesis advisor) / Gel, Esma (Committee member) / Shunk, Dan (Committee member) / Arizona State University (Publisher)
Created2012
154578-Thumbnail Image.png
Description
Buildings consume nearly 50% of the total energy in the United States, which drives the need to develop high-fidelity models for building energy systems. Extensive methods and techniques have been developed, studied, and applied to building energy simulation and forecasting, while most of work have focused on developing dedicated modeling

Buildings consume nearly 50% of the total energy in the United States, which drives the need to develop high-fidelity models for building energy systems. Extensive methods and techniques have been developed, studied, and applied to building energy simulation and forecasting, while most of work have focused on developing dedicated modeling approach for generic buildings. In this study, an integrated computationally efficient and high-fidelity building energy modeling framework is proposed, with the concentration on developing a generalized modeling approach for various types of buildings. First, a number of data-driven simulation models are reviewed and assessed on various types of computationally expensive simulation problems. Motivated by the conclusion that no model outperforms others if amortized over diverse problems, a meta-learning based recommendation system for data-driven simulation modeling is proposed. To test the feasibility of the proposed framework on the building energy system, an extended application of the recommendation system for short-term building energy forecasting is deployed on various buildings. Finally, Kalman filter-based data fusion technique is incorporated into the building recommendation system for on-line energy forecasting. Data fusion enables model calibration to update the state estimation in real-time, which filters out the noise and renders more accurate energy forecast. The framework is composed of two modules: off-line model recommendation module and on-line model calibration module. Specifically, the off-line model recommendation module includes 6 widely used data-driven simulation models, which are ranked by meta-learning recommendation system for off-line energy modeling on a given building scenario. Only a selective set of building physical and operational characteristic features is needed to complete the recommendation task. The on-line calibration module effectively addresses system uncertainties, where data fusion on off-line model is applied based on system identification and Kalman filtering methods. The developed data-driven modeling framework is validated on various genres of buildings, and the experimental results demonstrate desired performance on building energy forecasting in terms of accuracy and computational efficiency. The framework could be easily implemented into building energy model predictive control (MPC), demand response (DR) analysis and real-time operation decision support systems.
ContributorsCui, Can (Author) / Wu, Teresa (Thesis advisor) / Weir, Jeffery D. (Thesis advisor) / Li, Jing (Committee member) / Fowler, John (Committee member) / Hu, Mengqi (Committee member) / Arizona State University (Publisher)
Created2016
158723-Thumbnail Image.png
Description
This dissertation explores the use of deterministic scheduling theory for the design and development of practical manufacturing scheduling strategies as alternatives to current scheduling methods, particularly those used to minimize completion times and increase system capacity utilization. The efficient scheduling of production systems can make the difference between a thriving

This dissertation explores the use of deterministic scheduling theory for the design and development of practical manufacturing scheduling strategies as alternatives to current scheduling methods, particularly those used to minimize completion times and increase system capacity utilization. The efficient scheduling of production systems can make the difference between a thriving and a failing enterprise, especially when expanding capacity is limited by the lead time or the high cost of acquiring additional manufacturing resources. A multi-objective optimization (MOO) resource constrained parallel machine scheduling model with setups, machine eligibility restrictions, release and due dates with user interaction is developed for the scheduling of complex manufacturing systems encountered in the semiconductor and plastic injection molding industries, among others. Two mathematical formulations using the time-indexed Integer Programming (IP) model and the Diversity Maximization Approach (DMA) were developed to solve resource constrained problems found in the semiconductor industry. A heuristic was developed to find fast feasible solutions to prime the IP models. The resulting models are applied in two different ways: constructing schedules for tactical decision making and constructing Pareto efficient schedules with user interaction for strategic decision making aiming to provide insight to decision makers on multiple competing objectives.
Optimal solutions were found by the time-indexed IP model for 45 out of 45 scenarios in less than one hour for all the problem instance combinations where setups were not considered. Optimal solutions were found for 18 out of 45 scenarios in less than one hour for several combinations of problem instances with 10 and 25 jobs for the hybrid (IP and heuristic) model considering setups. Regarding the DMA MOO scheduling model, the complete efficient frontier (9 points) was found for a small size problem instance in 8 minutes, and a partial efficient frontier (29 points) was found for a medium sized problem instance in 183 hrs.
ContributorsMunoz-Estrada, Luis Fernando (Author) / Villalobos, Jesus R (Thesis advisor) / Fowler, John (Thesis advisor) / Rogers, Bradley (Committee member) / Arizona State University (Publisher)
Created2020