Matching Items (15)
Filtering by

Clear all filters

152178-Thumbnail Image.png
Description
The construction industry in India suffers from major time and cost overruns. Data from government and industry reports suggest that projects suffer from 20 to 25 percent time and cost overruns. Waste of resources has been identified as a major source of inefficiency. Despite a substantial increase in the past

The construction industry in India suffers from major time and cost overruns. Data from government and industry reports suggest that projects suffer from 20 to 25 percent time and cost overruns. Waste of resources has been identified as a major source of inefficiency. Despite a substantial increase in the past few years, demand for professionals and contractors still exceeds supply by a large margin. The traditional methods adopted in the Indian construction industry may not suffice the needs of this dynamic environment, as they have produced large inefficiencies. Innovative ways of procurement and project management can satisfy the needs aspired to as well as bring added value. The problems faced by the Indian construction industry are very similar to those faced by other developing countries. The objective of this paper is to discuss and analyze the economic concerns, inefficiencies and investigate a model that both explains the Indian construction industry structure and provides a framework to improve efficiencies. The Best Value (BV) model is examined as an approach to be adopted in lieu of the traditional approach. This could result in efficient construction projects by minimizing cost overruns and delays, which until now have been a rarity.
ContributorsNihas, Syed (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Kashiwagi, Jacob (Committee member) / Arizona State University (Publisher)
Created2013
152185-Thumbnail Image.png
Description
Over the past couple of decades, quality has been an area of increased focus. Multiple models and approaches have been proposed to measure the quality in the construction industry. This paper focuses on determining the quality of one of the types of roofing systems used in the construction industry, i.e.

Over the past couple of decades, quality has been an area of increased focus. Multiple models and approaches have been proposed to measure the quality in the construction industry. This paper focuses on determining the quality of one of the types of roofing systems used in the construction industry, i.e. Sprayed Polyurethane Foam Roofs (SPF roofs). Thirty seven urethane coated SPF roofs that were installed in 2005 / 2006 were visually inspected to measure the percentage of blisters and repairs three times over a period of 4 year, 6 year and 7 year marks. A repairing criteria was established after a 6 year mark based on the data that were reported to contractors as vulnerable roofs. Furthermore, the relation between four possible contributing time of installation factors i.e. contractor, demographics, season, and difficulty (number of penetrations and size of the roof in square feet) that could affect the quality of the roof was determined. Demographics and difficulty did not affect the quality of the roofs whereas the contractor and the season when the roof was installed did affect the quality of the roofs.
ContributorsGajjar, Dhaval (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Badger, William (Committee member) / Arizona State University (Publisher)
Created2013
150133-Thumbnail Image.png
Description
ABSTRACT Facility managers have an important job in today's competitive business world by caring for the backbone of the corporation's capital. Maintaining assets and the support efforts cause facility managers to fight an uphill battle to prove the worth of their organizations. This thesis will discuss the important and flexible

ABSTRACT Facility managers have an important job in today's competitive business world by caring for the backbone of the corporation's capital. Maintaining assets and the support efforts cause facility managers to fight an uphill battle to prove the worth of their organizations. This thesis will discuss the important and flexible use of measurement and leadership reports and the benefits of justifying the work required to maintain or upgrade a facility. The task is streamlined by invoking accountability to subject experts. The facility manager must trust in the ability of his or her work force to get the job done. However, with accountability comes increased risk. Even though accountability may not alleviate total control or cease reactionary actions, facility managers can develop key leadership based reports to reassign accountability and measure subject matter experts while simultaneously reducing reactionary actions leading to increased cost. Identifying and reassigning risk that are not controlled to subject matter experts is imperative for effective facility management leadership and allows facility managers to create an accurate and solid facility management plan, supports the organization's succession plan, and allows the organization to focus on key competencies.
ContributorsTellefsen, Thor (Author) / Sullivan, Kenneth (Thesis advisor) / Kashiwagi, Dean (Committee member) / Badger, William (Committee member) / Arizona State University (Publisher)
Created2011
149709-Thumbnail Image.png
Description
The price based marketplace has dominated the construction industry. The majority of owners use price based practices of management (expectation and decision making, control, direction, and inspection.) The price based/management and control paradigm has not worked. Clients have now been moving toward the best value environment (hire

The price based marketplace has dominated the construction industry. The majority of owners use price based practices of management (expectation and decision making, control, direction, and inspection.) The price based/management and control paradigm has not worked. Clients have now been moving toward the best value environment (hire contractors who know what they are doing, who preplan, and manage and minimize risk and deviation.) Owners are trying to move from client direction and control to hiring an expert and allowing them to do the quality control/risk management. The movement of environments changes the paradigm for the contractors from a reactive to a proactive, from a bureaucratic
on-accountable to an accountable position, from a relationship based
on-measuring to a measuring entity, and to a contractor who manages and minimizes the risk that they do not control. Years of price based practices have caused poor quality and low performance in the construction industry. This research identifies what is a best value contractor or vendor, what factors make up a best value vendor, and the methodology to transform a vendor to a best value vendor. It will use deductive logic, a case study to confirm the logic and the proposed methodology.
ContributorsPauli, Michele (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Badger, William (Committee member) / Arizona State University (Publisher)
Created2011
150372-Thumbnail Image.png
Description
As global competition continues to grow more disruptive, organizational change is an ever-present reality that affects companies in all industries at both the operational and strategic level. Organizational change capabilities have become a necessary aspect of existence for organizations in all industries worldwide. Research suggests that more than half of

As global competition continues to grow more disruptive, organizational change is an ever-present reality that affects companies in all industries at both the operational and strategic level. Organizational change capabilities have become a necessary aspect of existence for organizations in all industries worldwide. Research suggests that more than half of all organizational change efforts fail to achieve their original intended results, with some studies quoting failure rates as high as 70 percent. Exasperating this problem is the fact that no single change methodology has been universally accepted. This thesis examines two aspect of organizational change: the implementation of tactical and strategic initiatives, primarily focusing on successful tactical implementation techniques. This research proposed that tactical issues typically dominate the focus of change agents and recipients alike, often to the detriment of strategic level initiatives that are vital to the overall value and success of the organizational change effort. The Delphi method was employed to develop a tool to facilitate the initial implementation of organizational change such that tactical barriers were minimized and available resources for strategic initiatives were maximized. Feedback from two expert groups of change agents and change facilitators was solicited to develop the tool and evaluate its impact. Preliminary pilot testing of the tool confirmed the proposal and successfully served to minimize tactical barriers to organizational change.
ContributorsLines, Brian (Author) / Sullivan, Kenneth T. (Thesis advisor) / Badger, William (Committee member) / Kashiwagi, Dean (Committee member) / Arizona State University (Publisher)
Created2011
156379-Thumbnail Image.png
Description
Recent studies have identified that contractors in the Saudi construction industry are not the main party that cause risks as owners and other parties have the major share of causing risks. However, with the identification that risks out of contractors’ control are a leading cause of low performance, there is

Recent studies have identified that contractors in the Saudi construction industry are not the main party that cause risks as owners and other parties have the major share of causing risks. However, with the identification that risks out of contractors’ control are a leading cause of low performance, there is a lack of efficient risk mitigation practices in Saudi to manage these risks. The main aim of this dissertation is to assess the current practices applied by contractors to minimize risk out of their control and develop a risk mitigation model to manage these risks. The main objectives of the study are: investigating the risks that are out of contractors’ control, assessing the contractors’ current risk mitigation and performance measurement practices, and finally developing and validating a risk mitigation model to minimize risks out of contractors’ control and measure performance of involved project parties. To achieve the study aim, a mixed methodological approach was adopted. Theoretical approaches were utilized to review previous research and to develop a conceptual risk mitigation framework followed by a practical approach that is considered with collecting data from contractors. The quantitative method was mainly used to meet the study objectives through distributing a survey in the form of a questionnaire. As a consolidation of the study findings, the top ranked risks that are out of contractors’ control were identified. Furthermore, the results identified that the contractors’ current risk management and performance measurement practices are not effective in minimizing projects risks caused by other parties and ineffective in measuring performance of all parties. The developed model focuses on increasing accountability of project parties through mitigating project parties’ activities and risks with measuring the deviations and identifying sources of deviations. Transparency is utilized in the model through sharing weekly updates of the activities and risks combined with updated information of performance measurements of all project parties. The study results showed that project risks can be minimized and projects’ performance can be increased if contractors shift their focus using the developed model from only managing their own activities and risks to managing all project parties’ activities and risks.
ContributorsAlgahtany, Mohammed (Author) / Sullivan, Kenneth (Thesis advisor) / Kashiwagi, Dean (Committee member) / Badger, William (Committee member) / Arizona State University (Publisher)
Created2018
137112-Thumbnail Image.png
Description
Abstract The purpose of this project is to utilize the models and concepts from Information Measurement Theory (IMT) to help minimize future decision making with respect to my career path. When I began this project, my future was clouded, my initial conditions were unknown, my stress over future career-path decisions

Abstract The purpose of this project is to utilize the models and concepts from Information Measurement Theory (IMT) to help minimize future decision making with respect to my career path. When I began this project, my future was clouded, my initial conditions were unknown, my stress over future career-path decisions was high, and I had eight possible career paths in mind. I have narrowed my career-path options from eight to four. In addition, I have determined a one-year plan that enables me to be prepared to pursue any of the four career paths that I have found align with me. In this project, I explored my dominant initial conditions with respect to my career path. I tracked the job history of my grandparents and parents. These efforts allowed me to identify the strengths and weaknesses that I was exhibiting by the age of three. Natural law dictates that the strengths and weaknesses of my younger self will be the same strengths and weakness that I excel at and struggle with today. I then used my understanding of natural law and the event model process to map the strengths and weaknesses of my parents and grandparents and to compare and contrast these to my strengths and weaknesses, including those that were apparent by the time that I was three years old. Focusing in on what I really want from a job, four main goals were established to grade the various future career-path options. Finally, I documented my transition from uncertainty to clarity. It began with my sobriety and ended with a milestone one-year plan that will give me information that I need to commit to my career path. This transition has had significant impact. The elusive "who am I" has been addressed, not completely but addressed sufficiently so that the question no longer plagues me. I know from where I have come. I have gained significant insight from those around me who know me. All of this has been documented for my own personal use, and for my children someday. This process permitted me to eliminate outliers from my eight original career paths, reducing them to four. In addition, application of IMT models and concepts has allowed me to see one year into the future. With my new-found knowledge, I will listen and watch the doors close on three of the remaining four career paths, as there is only one path I am meant to take.
ContributorsRichardson, Trevor Woods (Author) / Kashiwagi, Dean (Thesis director) / Kashiwagi, Jacob (Committee member) / Industrial, Systems (Contributor) / Barrett, The Honors College (Contributor) / Del E. Webb Construction (Contributor)
Created2014-05
153848-Thumbnail Image.png
Description
ABSTRACT

The problem of litigation and disputes in the construction sector is a major impediment to countries’ development goals. The purpose of this paper is to investigate the problem of high legal costs and long delays that arise due to litigation involving project owners, designers, contractors and other construction parties

ABSTRACT

The problem of litigation and disputes in the construction sector is a major impediment to countries’ development goals. The purpose of this paper is to investigate the problem of high legal costs and long delays that arise due to litigation involving project owners, designers, contractors and other construction parties worldwide and in Saudi Arabia, as well as to give recommendation according to the outcomes of this research. The causes of litigious behavior in Saudi Arabia and other countries around the world were identified and documented, also the differences in litigation of the Saudi Arabian construction industry as compared to other countries were identified. Preliminary investigations revealed that there are some level of similarity in the nature of the causes. Thus, these causes were grouped into three main categories which are expectation factors, communications factors and documentation factors. Further research based on existing literature showed that the practices used to minimize litigation in the construction industry were investigated. The following delivery process were researched: design-build (DB) delivery method, Alliance Contracting, Construction Manager at Risk (CMAR), Best Value Approach, Integrated Project Delivery (IPD), and Public-Private Partnerships (PPPs), and the PIPS/PIRMS approach. These delivery methods were found to have issues, which means the methods by observation do not seem to be the ideal solution to minimize litigation in the construction industry. The only delivery method found to have no litigation issues was the PIPS/PIRMS approach.
ContributorsAlmutairi, Saud (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Kashiwagi, Jacob (Committee member) / Arizona State University (Publisher)
Created2015
153833-Thumbnail Image.png
Description
Delays are a major cause for concern in the construction industry both globally and locally in Saudi Arabia. This paper identifies the main causes of delay in infrastructure projects in the holy city of Makkah (Saudi Arabia) and compares these with projects around the rest of the country and other

Delays are a major cause for concern in the construction industry both globally and locally in Saudi Arabia. This paper identifies the main causes of delay in infrastructure projects in the holy city of Makkah (Saudi Arabia) and compares these with projects around the rest of the country and other Gulf countries as well. Data were obtained from 49 infrastructure projects that were undertaken by the owner and were analyzed quantitatively to understand the severity and causes of delay. 10 risk factors were identified in this study and these factors were grouped into four categories. The average delay in infrastructure projects in the city of Makkah was found to be 39%. The most severe cause of delay was found to be the land acquisition factor. This highlights the critical land ownership and acquisition issues that is prevailing in Makkah. In addition to this, other factors include contractors’ lack of expertise, haphazard underground utilities (line services), and re-designing. It is concluded that majority of delays were caused from the owner’s side as compared to contractors, consultants, and other project’s stakeholders. This finding was in line with the research findings of the Gulf Countries Construction (GCC) Industry’s literature as well. This study will fill an important practice and research gap for improving the efficiency in project delivery for infrastructure projects in the holy city of Makkah and the Gulf countries at large.
ContributorsElawi, Ghazi Saad A (Author) / Kashiwagi, Dean (Thesis advisor) / Sullivan, Kenneth (Committee member) / Kashiwagi, Jacob (Committee member) / Arizona State University (Publisher)
Created2015
155786-Thumbnail Image.png
Description
Public construction projects in Saudi Arabia have been experiencing performance issues for the past 30 years. There have been many research efforts and publications identifying the problem and potential causes, however, there have been minimal efforts identifying how to mitigate the problem and testing to validate proposed solutions. A literature

Public construction projects in Saudi Arabia have been experiencing performance issues for the past 30 years. There have been many research efforts and publications identifying the problem and potential causes, however, there have been minimal efforts identifying how to mitigate the problem and testing to validate proposed solutions. A literature search has shown that the academic research has had minimal impact in assisting the construction industry to improve its performance. This dissertation aimed to evaluate the impact of construction management research in Saudi construction industry (SCI), and to investigate barriers that hinder the diffusion of implementing the research outcomes in the construction sector in order to develop a research roadmap to bridge the gap between academic research and practice, using the experience of other organizations that have a successful experience in developing the impact of construction management research in the construction industry. In order to achieve the aim of the study, five main objectives were set up which are: evaluate the impact of construction management research in SCI, identify the barriers that affect the implementation of construction management research in SCI, develop a research roadmap to bridge the gap between the research and practice, validating the proposed solution, and proposed implementation plan and review the result from the implementation. A literature research was performed, using 5 academic databases, identifying the impact that R&D has had on the SCI. A questionnaire was also created surveying both researchers and industry professionals. The results show evidence that the current R&D process in Saudi Arabia is not helping the SCI to increase their performance, and needs to be improved. This study provides a potential solution, and an action plan that mirrors one of the most successful research and development programs in the construction industry in the world [+1915 tests, six different countries, 31 states in the U.S. and 98% customer satisfaction]. The solution proposed in this dissertation is unique to the strengths and weaknesses of the research and development programs at universities and research centers in Saudi Arabia. This study is the first study of its kind in Saudi Arabia.
ContributorsAlhammadi, Yasir (Author) / Kashiwagi, Dean (Thesis advisor) / Badger, William (Committee member) / Sullivan, Kenneth (Committee member) / Arizona State University (Publisher)
Created2017